Government is outlining both short-term relief and longer-term energy reforms as St. Maarten continues to deal with high electricity costs.
Prime Minister Dr. Luc Mercelina says GEBE is advancing plans for about 4 megawatts of ground-mounted solar at Hope Estate, along with roughly 2.5 megawatts of solar car-port capacity at the Walter Nisbeth Road parking lot.
The utility is also planning a major battery storage system with approximately 25 to 26 megawatt-hours of capacity and about 11 megawatts of inverter capacity. Proposed battery locations include Pond Island, Zagersgut and Mullet Bay.
Mercelina says the projects should strengthen the grid, improve energy security and reduce dependence on imported fossil fuels.
At the same time, MP Omar Ottley is pushing government to use the existing Price Ordinance as an interim measure while longer-term energy regulation is developed. His proposals include examining the profit margin on fuel sold to GEBE and improving transparency around water tariffs.
Mercelina has also announced an additional 400,000 guilders in GEBE-funded utility support for seniors and vulnerable households, bringing total assistance planned for 2027 to 1.5 million guilders.
VSA and GEBE are now working out how that assistance will be distributed.